Stay up to date with our digital construction diary, which documents the progress of the construction in detail.
Enjoy the impressive pictures that we regularly update for you and follow our success story as it continues to grow.


NIERUF CONSTRUCTION DIARY 2024

New company building in Besigheim

Our path into the future

We are pleased to present our construction project in Besigheim. Construction work on our new company site will begin in January 2025. This will not only lay the foundation for future growth, but will also increase the efficiency and modernity of our company.

With this project, we are creating a state-of-the-art working and storage environment that focuses on sustainable growth and innovative technology.

You can follow the progress of the project step by step in our construction diary. From the first earthworks to completion - we will keep you regularly informed with pictures and updates.

Stay tuned and follow the development of our new company site up close!

  • LOCATION
    Besigheim
  • OFFICE SPACE
    1.200 qm
  • STORAGE AREA
    1.700 qm
  • MODERN LOGISTICS
    Autostore
    System
  • START
    January 2025
  • INVESTMENT
    10 Mio. Euro
  • LOCATION
    Besigheim
  • OFFICE SPACE
    1.200 qm
  • STORAGE AREA
    1.700 qm
  • MODERN LOGISTICS
    Autostore
    System
  • START
    January 2025
  • INVESTMENT
    10 Mio. Euro
  • LOCATION
    Besigheim
  • OFFICE SPACE
    1.200 qm
  • STORAGE AREA
    1.700 qm
  • MODERN LOGISTICS
    Autostore
    System
  • START
    January 2025
  • INVESTMENT
    10 Mio. Euro

NIERUF CONSTRUCTION DIARY 2024

october 2024

The days are over …

The demolition of the old industrial hall has begun. Originally built in the 1960s as a sewing factory, it was a symbol of the economic boom. Generations of seamstresses worked here until textile production was moved abroad and the building was used as a warehouse and production facility for car windows.

The hall is now giving way to a modern office building with a warehouse, which will serve as the new headquarters for NieRuf. This will create a forward-looking site that combines the tradition of the location with new perspectives.

NIERUF CONSTRUCTION DIARY 2024

november 2024

Stone by stone

November brings great progress: The old industrial hall has been completely demolished and the materials have been carefully separated and disposed of professionally. The next step is to tackle the old floor slab and the asphalt, which will be crushed and sustainably reused on site following a thorough investigation by a geological survey.

Another milestone: the building permit has been received and all contracts with the Mörk company have been successfully signed. We are ready to tackle the next phase - step by step towards the future!

NIERUF CONSTRUCTION DIARY 2024

december 2024

Behind the scenes...

In December, we dedicate ourselves to the factory planning of our building, with the ambitious goal of creating a self-sufficient building that does not require fossil fuels. Modern technologies such as an efficient air heat pump and a powerful solar system are to ensure a sustainable energy supply and guarantee independence. The focus is also on design and appearance: our architect is working on the final design of the staircase, which will be a design highlight. At the same time, our employees gathered valuable ideas on the topic of “modern office worlds” in a workshop at Büroform in Murr. Technology and creativity come together step by step to create a building that impresses in terms of function, sustainability and aesthetics.

  • Okt 2024
  • Nov
  • Dez
  • Jan 2025
  • Feb
  • Mrz

FAQ

There for you


Special requests, spare parts or a quick support? Our staff will answer your questions and concerns immediately.

You can reach us from Monday to Friday at +497143 9666900 and any time at sales@nieruf.com

Catalog

Quality


Our certified quality management according to DIN EN ISO 9001: 2015 is part of our DNA. With our test stands we can carry out pressure tests with up to 350 bar with air and water as well as leak tests according to DIN EN 122661.

This is NieRuf


Committed

Commitment engenders trust. We stand by our word and are convinced that as a result not only our customers but also everyone we work with can rely on us.

Motivated

We always strive to find the best solution for our customers. It is our goal and incentive to have completely satisfied customers.

Competently

Technical and commercial expertise form the basis for developing qualified solutions tailored precisely to the needs of our customers.

Flexible

We do not adhere to rigid guidelines but instead focus on the individual wishes and needs of our customers. They are more important to us than internal company processes.